Mumbai-Ahmedabad Bullet Train To Be Fully Operational By 2029: Railway Minister Ashwini Vaishnaw

New Delhi: The Mumbai-Ahmedabad bullet train will be operational by 2029, and the 50-km stretch of India’s first high-speed rail corridor between Surat and Bilimora in Gujarat is expected to open by 2027, Union Railways Minister Ashwini Vaishnaw said on Saturday.

Vaishnaw inspected the under-construction Surat station, including track installation and the first turnout. According to him, people will be able to cover the distance between Mumbai and Ahmedabad in two hours and seven minutes on the bullet trains, against nine hours as shown on the Google Maps.

“Overall progress of the first bullet train project is very good. The first 50 km section between Surat and Bilimora will be open by 2027. By 2028, the Thane-Ahmedabad section will be commissioned, and by 2029, the full Mumbai-Ahmedabad line will open,” the minister said.

Add Zee News as a Preferred Source

Vaishnaw highlighted the use of modern technology to ensure safety, including vibration absorption mechanisms along the track and special safety features to handle high winds and earthquakes.

Heavy construction work at Surat station is complete, with finishing and utility work ongoing alongside track linking, the minister said. The first turnout, where tracks converge or diverge, has been installed with advanced technologies including roller bearings and composite sleepers.

The main line is designed for speeds up to 320 kilometres per hour, while the loop line will operate at 80 kilometres per hour. The services are designed such that a train will depart every half an hour during the morning and evening peak hours. Once the entire network stabilises, there will be a train every 10 minutes during peak hours, the minister had earlier said.

The project is expected to integrate the economies of major cities along the corridor and spur regional growth, similar to Japan’s growth story after its high-speed rail. The 508 km-long Mumbai-Ahmedabad high-speed rail corridor is India’s first bullet train project. The minister also indicated plans for four additional bullet train corridors in other regions of the country, as outlined in the BJP manifesto.

Continue reading

Laurence Fishburne on ‘The Matrix’ iconic look

Laurence Fishburne as rebel leader Morpheus has an iconic look in...

Skeletons in mass grave are ancient Roman soldiers, study finds

Scientists say seven skeletons found in a mass grave in Croatia were most likely Roman soldiers who lived 1,700 years ago.The male skeletons, all with various injuries, were found "completely preserved" during excavations in 2011 at the site of...